We completed a 1,975 square foot office design for our client, ifm electronic (HK) Limited, featuring a loft and natural style office design, delivered within 30 days.
We provide each client with detailed construction progress reports, including weekly on-site photos and comprehensive work descriptions. Even if you're too busy to visit the site in person, these reports keep you informed of the construction status at all times. Our team conducts regular on-site inspections to ensure all construction details meet your expectations.
Weekly office design follow-up
Week 1
Complete the installation of wires into the office wall
Office painting in progress
Week 2
Office building gypsum board wall installation completed
Office building soundproof wall installation completed
Week 3
Install all the wooden doors in the office building.
Begin laying office flooring
All office ceilings have been covered
Week 4
Office brand light box installation completed
Office feature wall installation completed
Apply frosted glass stickers to office glass